PHOTO: ANDY JACKSON/STUFF About 200 construction projects have had their start dates postponed, or have been put on hold or cancelled or had their completion delayed by Covid-19, a report says.
About 200 construction projects have been impacted by Covid 19 so far, according to a new report by building research firm Pacifecon.
RELATED: Will the New Zealand Housing Market Crash in 2020?
A Pacifecon report said 163 construction projects planned or tendered had had their start dates postponed.
Another seven planned or tendered projects had been placed on hold, two had been cancelled and 24 projects would have delayed completion.
“Approximately 200 projects, of thousands, are affected so far, but this is climbing daily.”